Relocations go wrong in a predictable way: material arrives, the new cabinets are not ready, boxes are stacked in a corridor, and six months later nobody knows which box holds 2019.
A relocation plan is mostly about sequencing and labelling. Neither is expensive; both are usually skipped.
1. Before the move
- Survey the new room: floor level, loading, door widths, power.
- Confirm the cabinet layout and numbering before anything is packed.
- Print drawer labels for the new system in advance.
- Book the move for a period when retrieval demand is low.
If the new archive uses compact shelving, the track must be installed and level before the first box arrives.
2. Packing by range, not by drawer
Pack in accession order, one box per drawer range, and label the box with the range and the destination drawer. Do not mix ranges in a box to fill space.
Keep blocks and slides from the same range together so a case can be verified without opening two boxes.
3. Transport
Blocks travel well in boxes; slides do not. Slides should move upright in trays or in the drawers themselves where the cabinet is being relocated intact. A box of loose slides will arrive with broken edges.
Label every box on two sides, and keep a manifest that lists box number, range and destination.
4. Placing and verifying
Place boxes in destination order before opening any of them. Then verify range by range: one person reads the label, another confirms the drawer.
Do not file the last box until the previous range is verified. Errors compound when verification is left to the end.
5. After the move
- Update the archive index with new locations.
- Run a sample audit: one drawer per cabinet.
- Record the move date in the archive log.
- Keep the manifest for at least one retention cycle.
6. Timing
A 100,000-slide archive typically takes two to four days to move with a small team, plus packing time. Add a buffer: the first day always runs slower than planned.
Common questions
Can cabinets be moved loaded?
Empty them first. A loaded cabinet is heavy, the drawers will open in transit, and the frame can twist.
Should we renumber during the move?
No. Move first, renumber later if necessary, and keep a crosswalk. Doing both at once doubles the error rate.